Infrastructure project on 2nd Avenue construction July 1-5

Friday, June 28, 2019

INFRASTRUCTURE UPGRADES ON 2ND AVE. AND SURROUNDING AREAS

PROJECT#: MED607

BOROUGH: MANHATTAN

DATE ISSUED: 06-28-19

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

  • NO WORK ON 7/4/19 THRU 7/7/19
  • WATER SHUT-OFF NOTIFICATIONS: 72-hour Advisory, a prior 24-hour notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction
  • areas.

FOR FURTHER INFORMATION: Contact Karen Flores, Community Construction Liaison, at (917) 631-5074 or 2ndaveccl@gmail.com.

DATE  WORK HOURS LOCATION  OPERATION
7/1/19 to 7/3/19  7am – 4pm 2nd Ave. between E 35th Street and E 36th Street Con Edison gas work (tie-in new mains)
7/1/19 to 7/3/19  7am – 4pm 1st Ave. between East 35th St and E 36th Street  Con Edison electrical work
7/1/19 to 7/3/19  7am – 4pm 3rd Ave. between E 32nd Street and E 34th Street  Con Edison steam work (excavate, demolish and dispose of existing abandoned steam main)
7/1/19 to 7/3/19  7am – 4pm 3rd Avenue between E 34th Street and E 36th Street  Install new 20” distribution water main
7/1/19 to 7/3/19  7am – 4pm E 33rd St between 2nd and 3rd Ave  ConEd gas service connections



 

RELATED DOCUMENTS

DDC flier

RELATED SITES

DDC Website

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today