MED607 2nd & 3rd Avenue Infrastructure construction February 25 - March 1

Tuesday, February 26, 2019

Infrastructure Upgrades on 2nd Ave. & Surrounding Areas

PROJECT #: MED607

BOROUGH: MANHATTAN

DATE ISSUED: 02/25/19


The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

NOTES:

  • THE CITY CONTRACTOR WILL BE WORKING NEXT SATURDAY 3/2/19. WORK WILL REFLECT ON NEXT FRIDAY’S WEEKLY LOOK AHEAD SCHEDULE.
  • COMMUNITY ADVISORIES: Will be email and/or hand distributed/posted 72 business hours prior to any work operations that will directly affect the community (i.e.) temporary bus stop relocations, water service interruptions, etc.
  • NO PARKING SIGNS: Will be distributed/posted 72 business hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: Contact Karen Flores, the Community Construction Liaison at (646) 768-9105 or 2ndaveccl@gmail.com
DATE TIME LOCATION OPERATION
2/25/19 - 3/01/19 7am – 3:30pm E. 33rd St. between 2nd Ave. and 3rd Ave Utility work- Welding 12” Gas Main
2/25/19 - 3/01/19 7am – 3:30pm 1st Ave. at intersection of E. 35th St & E. 33rd St. between 3rd Ave. and Lexington Ave. Utility work-Backfill Gas Main Trench
2/25/19 - 3/01/19 7am – 3:30pm West Side of 2nd Ave. between E. 35th St. & E. 36th St. Installation of the 20” Gas Main
2/25/19 - 3/01/19 7am – 3:30pm 3rd Ave. at E. 33rd St. Intersection & 3rd Ave. between E. 34th St. and E. 35th St. & 3rd Ave. between E. 35th St. and E. 36th St. Catch Basin Installation





 

RELATED DOCUMENTS

DDC flier

RELATED SITES

DDC Website

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today