Infrastructure Upgrades on 2nd Ave. & Surrounding Areas July 28 - August 4

Friday, July 27, 2018

Infrastructure Upgrades on 2nd Ave. & Surrounding Areas

PROJECT #: MED607

BOROUGH: MANHATTAN

DATE ISSUED: 07/27/18

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

NOTES:

**Please note Saturday work hours at specific intersections

WHEN THE CITY CONTRACTOR PLANS TO PERFORM A TEST AND/OR WATER SERVICE INTERRUPTION, AFFECTED LOCATIONS WILL BE NOTIFIED AS STATED BELOW:

  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour email distributed Community Advisory, a prior 24-hour official water shut off notification will be hand distributed / posted to any and/or all affected locations(s).
     
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
     
  • FOR FURTHER INFORMATION: Contact Karen Flores, the Community Construction Liaison at (646) 768-9105 or 2ndaveccl@gmail.com.
DATE WORK HOURS LOCATION OPERATION
**07/28/18 8am – 4:30pm E. 35th St. @ 2nd Ave. Intersection & E. 35th St. bet 2nd Ave. and QMT Approach Excavation for utility work test pits
07/28/18
08/04/18
7am –
3:30pm
E. 35th St. @ 1st Ave. Intersection Excavation for utility work test pits
07/28/18 
08/04/18
7am –
3:30pm
E. 33rd St. @ 3rd Ave. Intersection Excavation for utility work test pits
**08/04/18 8am –
4:30pm
E. 35th St. @ 2nd Ave. Intersection & E. 35th St. bet 2nd Ave. and QMT Approach Excavation for utility work test pits






 

 

 






 

 


 

RELATED DOCUMENTS

DDC Flier

RELATED SITES

DDC website

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today