Pershing Square West construction November 26 - December 2

Friday, November 24, 2017

PERSHING SQUARE WEST RECONSTRUCTION PROJECT

PROJECT #: HWPLZ004M

BOROUGH: MANHATTAN

DATE ISSUED: 11/22/17

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

NOTES:

  • No work scheduled for Thursday, 11/23 (day & night), in observance of the Thanksgiving Day Holiday.
  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour Advisory, a 24-hour prior notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: Contact Myriam Benjamin, the Community Construction Liaison at (646) 895-9271 or PershingSqPlzCCL@gmail.com

 

DATE  WORK HOURS LOCATION OPERATION
11/26/17 · 12/02/17 10pm to 6am East 40th St. between Park Ave. West and Madison Ave. Continue Excavation and Installation of 36 inch Trunk Water Main
11/27/17 · 12/01/17 7am to 3:30pm Park Ave. West between East 41st St. and East 42nd St. Plaza Construction ·Gas Line Installation (in progress)

RELATED DOCUMENTS

DDC Flier

RELATED SITES

DDC website

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today