Pershing Square Construction September 3-9

Monday, September 4, 2017

PERSHING SQUARE WEST RECONSTRUCTION PROJECT

PROJECT #: HWPLZ004M

BOROUGH: MANHATTAN

DATE ISSUED: 09/01/17

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

  • NOTE: No work scheduled for Saturday 9/2, Sunday night, 9/3 and Monday night, 9/4 in observance of the Labor Day Holiday.
  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour Advisory, a 24-hour prior notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: erContact Myriam Benjamin, the Community Construction Liaison at (646) 895-9271 or PershingSqPlzCCL@gmail.com

 

DATE WORK HOURS LOCATION OPERATION
9/05/17 to 9/09/17 9pm to 6am East 42nd St. between Vanderbilt Ave. and Lexington Ave. Roadway Excavation and Installation of Concrete Base
9/05/17 to 9/09/17 10pm to 6am East 40th St. between Park Ave. and Madison Ave. Excavation for Installation of 36 inch Trunk Water Main
9/05/17 to 9/09/17 10pm to 6am Park Ave. West between East 40th St. and East 39th St. Installation of 48 inch Trunk Water Main
9/05/17 to 9/09/17 7am to 3:30pm Park Ave. West between East 41st St. and East 42nd St. Plaza Construction (in progress)

 

 

RELATED DOCUMENTS

DDC Flyer

RELATED SITES

DDC WEBSITE

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today