The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

NOTES:

  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour Advisory, a 24-hour prior notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: Contact Myriam Benjamin, the Community Construction Liaison at (646) 895-9271 or PershingSqPlzCCL@gmail.com.

 

DATE WORK HOURS LOCATION OPERATION
08/13/17 to 08/19/17 9pm to 6am East 42nd St. between Vanderbilt Ave. and Lexington Ave. Roadway Excavation and Installation of Concrete Base
08/13/17 to 08/19/17 10pm to 6am East 40th St. between Park Ave. and Madison Ave. Excavation for Installation of 36 inch Trunk Water Main
08/14/17 to 08/19/17 7am to 3:30pm Park Ave. West between East 41st St. and East 42nd St. Plaza Construction (in progress)

 

RELATED DOCUMENTS

DDC Flyer

RELATED SITES

DDC WEBSITE

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today