Pershing Square Construction July 16-22

Friday, July 14, 2017

Updated 7/19/17

PERSHING SQUARE WEST RECONSTRUCTION PROJECT

PROJECT #: HWPLZ004M

BOROUGH: MANHATTAN

DATE ISSUED: 07/14/17

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

Work will be done in the daytime and during the night for the plaza reconstruction. This work is expected to last approximately 4 months.

NOTES:

  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour Advisory, a 24-hour prior notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: Contact Myriam Benjamin, the Community Construction Liaison at (646) 895-9271 or PershingSqPlzCCL@gmail.com

 

DATE WORK HOURS LOCATION OPERATION
07/19/17 ·07/22/17  10pm to 6am East 42nd St. between Vanderbilt Ave. and Lexington Ave. Anticipated Start of Full Roadway Restoration
07/16/17 ·07/22/17 10pm
 to 6am 
Park Ave. West between East 40th St. and East 39th St. Excavation for Installation of 48 inch Trunk Water Main
07/16/17 ·07/22/17  10pm to 6am Park Ave. West between East 41st St. and East 40th St. 36 inch Trunk Water Main Trench Restoration
07/19/17 ·07/22/17 - postponned until 7/24/17

7am to 3:30pm
and
10pm to 6am

Park Ave. West between East 41st St. and East 42nd St. Anticipated Start of Plaza Construction

RELATED DOCUMENTS

DDC Announcement - Daytime Work Hours
DDC Flyer

RELATED SITES

DDC WEBSITE

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today