Pershing Square Construction June 11-17

Monday, June 12, 2017

PERSHING SQUARE WEST RECONSTRUCTION PROJECT

PROJECT #: HWPLZ004M

BOROUGH: MANHATTAN

DATE ISSUED: 6/09/17

The following is an anticipated work schedule for the upcoming week. However, due to unforeseen field and weather conditions, it may become necessary to change some scheduled work locations, operations and dates.

  • WATER SHUT-OFF NOTIFICATIONS: In addition to a 72-hour Advisory, a 24-hour prior notification will be distributed / posted to any / all affected locations(s).
  • NO PARKING SIGNS: Will be distributed / posted 72 hours prior to the temporary elimination of street parking. Please observe posted parking regulations in construction areas.
  • FOR FURTHER INFORMATION: Contact Myriam Benjamin, the Community Construction Liaison at 646-895-9271 or PershingSqPlzCCL@gmail.com

 

DATE WORK HOURS LOCATION OPERATION
6/11/17 – 6/17/17 10pm to 6am East 42nd St. between Park Ave. and Lexington Ave. 12 inch Water Main Connection Work (north side) & 36 inch Trunk Water Main Work
6/11/17 – 6/17/17 10pm to 6am Park Ave. West between East 42nd St. and East 41st St. 36 inch Trunk Water Main Concrete Encasement & Utility Relocation
6/11/17 – 6/17/17 10pm to 6am Park Ave. West between East 41st St. and East 39th St. Excavation for Installation of 36 inch Trunk Water Main
 
6/11/17 – 6/17/17 10pm to 6am East 41st St. between Park Ave. East and Park Ave. West Catch Basin Installation and Chute Connection

 


 

RELATED DOCUMENTS

DDC Flyer

RELATED SITES

DDC website

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today