Park Avenue Tunnel Closure Weeknights and Weekends April 3 - June 30

Monday, March 27, 2017

Source: NYC Department of Transportation


Park Avenue Tunnel Closure Weeknights and Weekends April 3 - June 30

Beginning April 3, 2017, and continuing for approximately three months, the NYC Department of Transportation, Division of Bridges, will close the Park Avenue Tunnel to excavate and prepare the tunnel for installation of the new below grade drainage system. The Park Avenue Tunnel runs from 33rd Street to 40th Street on Park Avenue.

Work will take place weeknights between 9pm and 6am the following morning and 9pm Friday through 6am Monday morning. During the tunnel closures, traffic will be routed to the adjacent northbound service road (east side of Park Avenue). Drivers who want to go onto the elevated roadway around Grand Central Terminal should stay in the left lane as they approach 40th Street.

Tunnel Closure

April 3rd to June 30th, 2017
Weeknights: 9pm to 6am
Weekends: 9pm Friday to 6am Monday
The tunnel will re-open at 6am weekday mornings

Patty Sarantakos from The LiRo Group is available to provide information about this project at 646-476-0804 or parkavenuetunnel2016@gmail.com. For all NYC non-emergency services, including inquiries regarding NYCDOT construction projects, dial 311. Be prepared to give your name, the borough of the project, and a return phone number.

Park Avenue Tunnel Rehabilitation
HBM551
 

RELATED DOCUMENTS

March 27, 2017 Notice of Tunnel Closure

RELATED SITES

Project Scope

 

Join The Murray Hill Neighborhood Association

Be involved in the preservation, beautification and improvement of this very special neighborhood, and receive discounts at some of the finest Murray Hill restaurants and merchants.


Join Today